John Hyland Construction is setting up to demolish and rebuild most of Sweet Home High School.
Crews started removing asbestos from the building last week, Senior Project Manager Mike Mueller said. The majority of the asbestos removal is in the floor tiles.
He anticipates about three weeks on asbestos removal then demolition can begin on the $7 million project.
The reconstruction of the high school is part of an $18.6 million bond approved by Sweet…